ICMS Cost definitions
Cost categories
Costs are categorised into four levels as follows:
- level 1: project or subproject
- level 2: cost categories
- level 3: cost groups
- level 4: cost sub-groups
Demolition, site preparation and formation
Parent: Maintenance CostsDemolition, site preparation and formation costs include:
- Site survey and ground investigation
- Environmental treatment
- Sampling of hazardous or useful materials or conditions
- Temporary fencing
- Demolition of existing buildings and support to adjacent structures
- Site surface clearance (clearing, grubbing, topsoil stripping, tree felling, minor earthwork, removal)
- Tree transplant
- Site formation and slope treatment
- Temporary surface drainage and dewatering
- Temporary protection, diversion and relocation of public utilities
- Erosion control