ICMS Cost definitions
Cost categories
Costs are categorised into four levels as follows:
- level 1: project or subproject
- level 2: cost categories
- level 3: cost groups
- level 4: cost sub-groups
Construction Costs
Level 2 costs are frequently used to define the cost categorisation of a project based on these definitions:
- Acquisition costs
- Construction costs
- Renewal costs
- Operation costs
- Maintenance costs
- End of life costs
Construction Costs costs include:
- Demolition, site preparation and formation
- Substructure
- Structure
- Architectural works | non-structural works
- Services and equipment
- Surface and underground drainage
- External and ancillary works
- Preliminaries | Constructor’s site overheads | general requirements
- Risk Allowances
- Taxes and Levies
- Work and utilities off-site
- Post-completion furniture, furnishing and equipment
- Construction-related consultants and supervision